Prevent task updating
You can lock project tasks in order to prevent people from submitting task updates.
Note: Changes to task updating will not take effect until the next time that the project is published.
Note: You must have administrator permissions in order to prevent task updating.
-
On the Quick Launch, click Server Settings.
-
On the Server Settings page, click Close Tasks to Update.
-
On the Close Tasks to Update page, in the Select a project list, click the project that contains that task you want to close for updating.
-
In the Select Tasks section, select the check box for each task that you want to close to updating in the Lock column.
-
Do one of the following:
-
To publish your project and apply the changes you've made to closed task, click Publish.
-
To save your changes without publishing the project, click Submit. You must publish your project later in order to apply the changes you've make to task updating.
-