Specifications for Microsoft Project

Specifications for Microsoft Project

The following specifications are supported for Project 2013 and Project 2016, although actual limits and performance speed depend on your computer's configuration.

Note: Out-of-memory errors may occur before you reach the listed limits.

Attribute

Maximum

Resources per project

700,000

Resource units per assignment

60,000,000 units or 6,000,000,000%

Resource availability dates

100

Tasks per project

400,000

Task dependencies per project

No limit

Predecessors per task

50,000

Successors per task

50,000

Outline levels per project

65,535

Consolidated projects

998

Open project files per consolidated project

998

Sharer files connected to a single resource pool

997

(That is, the maximum number of open project files, minus 1 for the resource pool itself.)

Open windows

50

Base calendars

Tested to 30,000+

Calendar exceptions per calendar

Testing was able to add more than 15,000 exceptions to a base calendar.

Rate tables to support varying pay scales and rates

5 per resource

Variable rates per rate table to support rate increases and decreases

25

Cost value in a currency field

999,999,999,999.99

Work value

1,666,666,666 hours

Assignment work values for work assignments

999,999,999 hours

Assignment work values for variable material assignments

999,999,999 units

Assignment work values for fixed material assignments

60,000,000 units

Custom cell formats

64,000

Print scaling adjustment range percentage

10%-500%

Page header text

5 lines

Page footer text

3 lines

Page legend text

3 lines

Page legend text box width

5 inches (12.7 centimeters)

Filter tests per filter

40

Filter tests per AutoFilter

2 per column

Earliest date allowed for calculation

January 1, 1984

Latest date allowed for calculation

December 31, 2149

Discontinuous selections in a sheet view

10

Baselines

11

Characters in a text field

255

Characters in an outline code field

255

Values and characters in an Enterprise Resource Multi-Value (ERMV) field

255 values, each of 255 characters

Value in a number field

9,999,999,999,999.99

Add cell borders

Add cell borders

You can add a border around cells to emphasize data, mark summarized values, or separate data in cell ranges. Here's how:

  1. Select the cell or range of cells that you want to add a border around.

  2. Click Home > the Borders arrow, and then pick the border option you want.

    Tip:  The Borders button shows the most recently used border style. To apply that style, click the Borders button (not the arrow).

    the arrow next to the Borders button.

    To remove a border, select the cells with the border and click the Borders arrow > No Border.

Transfer workflows between SharePoint Designer and Visio

Transfer workflows between SharePoint Designer and Visio

In Microsoft SharePoint Designer 2010, you can import a workflow created in Microsoft Visio Premium 2010 or export a workflow to Visio for viewing. Business analysts and process analysts who are already familiar with flowcharting in Visio can use Visio to design a workflow that represents their business logic, export the workflow, and enable a site owner or IT professional using SharePoint Designer to implement it in a form that can be automated in SharePoint 2010.

Translate business logic in Visio to workflow rules in SharePoint Designer

In addition, there are two ways that workflows in SharePoint Designer can be visualized:

  • If Visio Services is installed on the SharePoint 2010 server, you can create a workflow visualization on the workflow status page that displays progress and assignments.

  • You can export the workflow to Visio to create a workflow drawing that can be used for feedback and approval.

Workflow diagrams can be exported to Visio

What do you want to do?

Import a workflow from Visio

Export a workflow to Visio

Visualize a workflow in SharePoint 2010 with Visio Services

Import a workflow from Visio

To import a SharePoint workflow, do the following:

  1. In SharePoint Designer 2010, in the Navigation pane, click Workflows.

  2. On the Workflows tab, in the Manage group, click Import from Visio.
    Import workflow

  3. In the Import Workflow from Visio Drawing dialog box, browse to and select the Visio Workflow Interchange (.vwi) file you want to use, and then click Next.

  4. Type a name for the workflow, and then select the type of workflow you want it to be once it has been imported. Your choices are:

    1. List workflow    – a workflow that is attached to a specific list. If you select this option, you must choose the list to which the workflow will be attached.

    2. Reusable workflow    – a workflow that is attached to a content type, and is therefore portable. It can be used by different lists on a SharePoint site. If you select this option, you must choose the content type on which the workflow will run.

  5. Click Finish.

The imported workflow appears in SharePoint Designer's full-screen workflow editor. All custom shape text in the Visio diagram is imported into SharePoint Designer as activity labels (the gray text in the image below) to clarify the intent of the workflow:

Imported workflow

Once imported to SharePoint Designer, the workflow is editable and can be revised to add the necessary conditions, actions, steps, and settings. For more information about editing workflows, see Introduction to designing and customizing workflows

Top of Page

Export a workflow to Visio

Once you have created or edited a workflow in SharePoint Designer 2010, you can export the workflow as a Visio drawing that can be opened in Visio Premium 2010. The ability to import a workflow back to Visio after having been edited in SharePoint Designer, also known as "round-tripping," enables deeper collaboration between business users and workflow designers. When iterating the workflow design in this way, you can use Visio to define the business requirements, and then use round-tripping as a way to coordinate and approve changes.

Note:  Visio Premium 2010 does not support steps. Step information that has been added in SharePoint Designer may be lost when the workflow is viewed in Visio and then re-imported into SharePoint Designer.

To export a workflow, do the following:

  1. In SharePoint Designer 2010, click Workflows in the Navigation pane.

  2. On the Workflow tab, in the Manage group, click Export to Visio.

  3. In the Export Workflow to Visio Drawing dialog box, name the file, select a location, and then click Save. The exported file is saved as a .vwi file that can be opened directly in Visio Premium 2010.

Top of Page

Visualize a workflow in SharePoint 2010 with Visio Services

Using SharePoint Designer 2010, you can enable workflow visualization on the workflow status page. This enables users to track the progress of the workflow visually during its execution. For example, the workflow visualization below shows tasks that are "in progress" and tasks that are "completed." The people assigned to the tasks are also displayed clearly within the task shapes.

SharePoint workflow visualization

To add a workflow visualization to the workflow status page, do the following:

  1. In SharePoint Designer 2010, click Workflows in the Navigation pane, and then click the workflow that you want to visualize.

  2. On the summary page for that workflow, under Settings, check the Show workflow visualization on status page box.

    Note:  Visio Services must be enabled on the SharePoint Server 2010 and Visio Premium 2010 must be installed on the same machine as SharePoint Designer 2010.

Top of Page