Saturday, March 19, 2022

Bcws planned value or pv fields

The BCWS (budgeted cost of work scheduled) fields contain the cumulative timephased baseline costs up to the status date or today's date. The timephased versions of these fields show values distributed over time.

There are several categories of BCWS fields.

Data Type    Currency

BCWS (task field)

Entry Type    Calculated

How Calculated    To calculate BCWS for a task, Microsoft Office Project adds the timephased baseline costs of the task up to the status date.

Best Uses    Add the BCWS field to a task sheet to review how much of the budget should have been spent on a task to date, according to the task's baseline cost.

Example    The baseline cost for a task is $500 and is evenly distributed over its duration. The baseline start for the task is June 1, and the baseline finish is August 1. If today's date is July 1, then the BCWS for the task is $250, since the task should be half done.

Remarks    You can compare the BCWS to the BCWP (budgeted cost of work performed) field to determine whether the task is behind or ahead of schedule in terms of cost. The SV (earned value schedule variance) field shows the comparison of these fields over time.

BCWS (resource field)

Entry Type    Calculated

How Calculated    To calculate BCWS for a resource, Microsoft Office Project adds the timephased baseline costs of the resource up to the status date.

Best Uses    Add the BCWS field to a resource sheet to review how much of the budget should have been spent on a resource to date.

Example    Sean has a BCWS of $100 on one assigned task, $200 on another assigned task, and $50 on a third assigned task. In the Resource Sheet view, you see that Sean has a rolled up BCWS of $350 up to the status date.

Remarks    You can compare the BCWS to the BCWP (budgeted cost of work performed) field to determine whether the resource is behind or ahead of schedule in terms of cost. The SV (earned value schedule variance) field shows the comparison of these fields.

BCWS (assignment field)

Entry Type    Calculated

How Calculated    To calculate BCWS for the assignment, Microsoft Office Project adds the timephased baseline costs of an assignment up to the status date or today's date.

Best Uses    Add the BCWS field to the timephased portion of the Task Usage or Resource Usage view to review how much of the budget should have been spent on an assignment to date.

Example    The baseline cost for an assignment is $500 and is evenly distributed over its duration. The baseline start for the assignment is June 1, and the baseline finish is August 1. If today's date is July 1, then the BCWS for the assignment is $250.

Remarks    You can compare BCWS to the BCWP (budgeted cost of work performed) field to determine whether the assignment is behind or ahead of schedule in terms of cost. The SV (earned value schedule variance) field shows the comparison of these fields over time.

BCWS (task-timephased field)

Entry Type    Calculated

How Calculated    To calculate timephased BCWS for a task, Microsoft Office Project adds the cumulative timephased baseline costs up to the status date.

Best Uses    Add the BCWS field to the timephased portion of the Task Usage view to display how much of the budget should have been spent on a task. Also, use this field to plot BCWS on an S-curve graph.

Example    The baseline cost for a task is $500, and is evenly distributed over its duration. The baseline start for the task is June 1, and the baseline finish is August 1. If today's date is July 1, then the BCWS is $250. On June 1, the timephased value is $12.50. On June 2, the value is $25. On June 3, the value is $37.50. On June 4, the value is $50. The timephased values are shown in this manner, distributed and accumulated across the month of June, until you see the total BCWS of $250 on July 1.

Remarks    You can compare BCWS to the BCWP (budgeted cost of work performed) field to determine whether the task is behind or ahead of schedule in terms of cost. The timephased SV (earned value schedule variance) field shows the comparison of these fields.

BCWS (resource-timephased field)

Entry Type    Calculated

How Calculated    To calculate timephased BCWS for a resource, Microsoft Office Project adds the timephased baseline costs of the resource up to the status date.

Best Uses    Add the BCWS field to the timephased portion of the Resource Usage view. You'll display how much of the budget should have been spent on a resource to date. You can also use this field to plot BCWS on an S-curve graph.

Example    Sean has a BCWS of $100 on one assigned task, $50 on another assigned task, and $50 on a third assigned task. In the timephased portion of the Resource Usage view, the past four days show the timephased BCWS as $50, $100, $150, and $200.

Remarks    You can compare the BCWS to the BCWP (budgeted cost of work performed) field to determine whether the resource is behind or ahead of schedule in terms of cost. The timephased SV (earned value schedule variance) field shows the comparison of these fields over time.

BCWS (assignment-timephased field)

Entry Type    Calculated

How Calculated    To calculate timephased BCWS for an assignment, Microsoft Office Project adds the timephased baseline costs on the assignment up to the status date of the project.

Best Uses    Add the BCWS field to the timephased portion of the Task Usage or Resource Usage view. This field displays how much of the budget should have been spent on an assignment to date. You can also use this field to plot BCWS on an S-curve graph.

Example    The baseline cost for an assignment is $500 and is evenly distributed over its duration. The baseline start for the assignment is June 1, and the baseline finish is August 1. If today's date is July 1, then the BCWS is $250. On June 1, the timephased value is $12.50. On June 2, the value is $25. On June 3, the value is $37.50. On June 4, the value is $50. The timephased values are shown in this manner, accumulated and distributed across the month of June, until you see the total BCWS of $250 on July 1.

Remarks    You can compare the BCWS to the BCWP (budgeted cost of work performed) field to determine whether the assignment is behind or ahead of schedule in terms of cost. The timephased SV (earned value schedule variance) field shows the comparison of these fields over time.

4 comments:

  1. Special thanks to HACK VANISH, a professional hacker I’ve been hiring for the past 2 years because, I find him to be an outstanding hacker who has aided me in various hacking related issues, ranging from fixing my poor FICO credit score of about 437 TransUnion, 462 Equifax to 802 plus excellent score, tracking my cheating husband’s phone and currently has helped me recover my lost crypto funds from an online scam investment I recently ventured into, I must confess he is the best, quite brilliant, ever since I discovered him through a positive review I saw on Wallet Hub and reached out to him via Email: Hackvanish @ Gmail. com, and Phone: +1(747) 293-8514, to which he responded in less than 10mins, I have never regretted working with him, he’s been quite helpful and highly efficient. I Would recommend his services to anyone without hesitation.

    ReplyDelete
  2. I'm so happy to share this with you that can read / see this now. When I started trading binary and forex a few months ago, I really didn't have the necessary tools to trade and I lost a lot until I met Pablo Martinez who taught me all about market psychology as he managed my account for me. Today I am grateful to him for his great offer and help because it really changed my financial situation with an investment capital of $1500 and now I'm earning around $35,500 - $30,000 profits per week. Here is his WhatsApp no: +44 7520 636249 or his email address: pm7234029@gmail.com
    Https://www.facebook.com/PM-Fast-Trade-104912912155335/

    ReplyDelete
  3. You need personal informations from companies,family and friends that will better your life and you need easy access without them noticing or you’re financially unstable and you have a bad credit score, come to Brillianthackers800@gmail.com he will solve that without stress,he and his team can clear criminal records without leaving a trace and can also anonymously credit your empty credit cards with funds you need,all these things and more this hacker and his team will do cause they keep you updated on every step taken in order to achieve the goal and they also deliver on time,I tested and confirmed this I’m still happy on how my life is improving after my encounter with them, you can send a mail to Brillianthackers800@gmail.com

    ReplyDelete
  4. Months ago I planted a seed here. My credit report was lit in red like a Christmas tree of nothing but bad checks. My goal at first was a 680 score, to qualify for a mortgage. That turned into 700…then 710…eventually I entered the 800 club. That 800 club then got me into the 800 teen club. Today I was notified that my Equifax passed the 800 teen club. 821! What was hard to qualify for a $500 credit card now makes it easy to get a $5000 credit card. What was hard to get a $1 credit line increase, makes it easy to get $1000. What was hard to get a lower credit card interest (that actually resulted in getting higher interest) now is easy to make and generally results in a lower rate. How I got to this point was from the help of PINNACLE CREDIT SPECIALIST and the help I received from this board. It takes time, effort and determination. The pay in the end is great. I don’t regret working with PINNACLE CREDIT SPECIALIST. When I started I wanted everything fixed overnight but he said no he has to go one bit at a time to avoid a trace. He started with what they know is easy and worked my credit up. That’s how I got here. His an angel in human form don’t fail to hit him up on email: PINNACLECREDITSPECIALIST@GMAIL.COM

    ReplyDelete