Change when a task becomes critical
By default, Microsoft Office Project defines a task as critical if it has zero days of slack. However, you can change this definition and make a task critical if it has, for example, one or two days of slack.
-
On the Tools menu, click Options, and then click the Calculation tab.
-
In the Tasks are critical if slack is less than or equal to box, type or select the number of slack days. If the number of slack days for a task is less than or equal to the number that you specify here, the task is considered critical.
-
Click Set as Default if you want to make this setting the default for all your projects.