Data Type Text
Entry Type Calculated
Description The Task Calendar GUID field contains the generated unique identification codes for each task calendar in your project. No two task calendars will have the same Task Calendar GUID.
How Calculated As soon as you assign a calendar to a task, automatically creates a task calendar along with its unique identifier. This identifier is stored in the Task Calendar GUID field.
Best Uses Insert the Task Calendar GUID column into a task sheet when you need to see the unique identifier for each task calendar. This is particularly useful to help with programming and debugging custom applications.
Example You are creating a macro that references specific resource calendars in your project. To obtain the unique identifiers for these calendars, you insert the Task Calendar GUID column into the Task Sheet.
No comments:
Post a Comment