Monday, August 7, 2017

Remove a split in a task

Remove a split in a task

  1. On the View menu, click Gantt Chart.

  2. In the chart portion of the Gantt Chart view, point to the Gantt bar representing the portion of the task that has been delayed.

    The pointer changes to a four-pointed arrow. Four-sided arrow on Gantt Bar

  3. Drag the Gantt bar to the left until it meets the portion of the Gantt bar representing the work already done on the task.