In Project, the default task duration unit is days, but you can change it to be minutes, hours, weeks, or months:
-
Choose File > Options.
-
In the Project Options dialog box, choose Schedule.
-
Under Scheduling options for this project, in the Duration is entered in list, select a duration unit.
-
To use the same setting automatically in all future projects, select All New Projects in the Scheduling options for this project list.
Hello guys, I just want to share my joyful experience about HACK VANISH CREDIT SPECIALIST. Before the coronavirus pandemic, I had criminal Judgments, few evictions, and late payment which negatively impacted my credit score down to 487 and left me in difficult financial situation, as a single mum of 3, I needed a loan to keep the family running after I lost my husband as a result of COVID-19, all hope were lost, until Mrs. Olivia referred me to HACK VANISH, a credit genius who was very helpful in fixing my credit 6 days after I reached out to him via Email: hackvanish (At) gmail (Dot) com and Phone: +1(747) 293-8514, throughout the process, I felt so involved because an open line of communication was maintained till I got my FICO score restored to 796, currently my loan application has been approved. If you need to hire a credible hacker, HACK VANISH is highly recommended.
ReplyDelete