Task fields
The following are the task fields in Microsoft Office Project. For more information, click a field name.
Baseline Duration (task field)
Baseline1-10 Duration (task fields)
Duration Variance (task field)
Earned Value Method (task field)
Enterprise Duration1-10 fields
Enterprise Task Outline Code1-30 (task fields)
Expected Duration (task field)
Ignore Resource Calendar (task field)
Level Assignments (task field)
Leveling Can Split (task field)
Optimistic Duration (task field)
Optimistic Finish (task field)
Percent (%) Work Complete fields
Pessimistic Duration (task field)
Pessimistic Finish (task field)
Pessimistic Start (task field)
Physical Percent (%) Complete (task field)
Preleveled Finish (task field)
Remaining Duration (task field)
Remaining Overtime Cost fields
Remaining Overtime Work fields
Resource Phonetics (task field)
Subproject Read Only (task field)
Unique ID Predecessors (task field)
No comments:
Post a Comment