Import data from Project into a Visio Gantt chart
If you want to use data from Microsoft Office Project to create a Gantt chart in Microsoft Office Visio, you can use the Import Project Data Wizard to import that data into Visio.
Note: To import data from Microsoft Office Project, you must have Project installed on your machine.
-
On the File menu in Visio, point to New, point to Schedule, click Gantt Chart, and then click Cancel.
-
On the Gantt Chart menu, click Import.
-
On the first wizard page, click Information that's already stored in a file.
-
On the next wizard page, under Select the format of your project data, click Project File, and then click Next.
-
On the next wizard page, click Browse to locate the Project file from which you want to create a Gantt chart. Select the file, click Open, and then click Next.
-
Follow the wizard pages to create your Gantt chart.