Saturday, July 31, 2021

Finish task field

Data Type    Date

Entry Type    Calculated or entered

Description    The Finish field shows the date when a task is scheduled to be completed. You can have Project calculate the finish date or you can enter it yourself.

How Calculated    Project calculates the finish date based on the start date, task duration, task dependencies, the project calendar, and other task constraints. If resources are assigned, Project also considers the resource calendar and assignment units.

If you enter a finish date for an automatically scheduled task, Project assigns a Finish No Earlier Than constraint to the task and uses your entered finish date as the constraint date. If your project schedules from the finish date, and if you enter a finish date, Project automatically applies a Finish No Later Than constraint to the task.

If you are using Project 2010, and you enter a finish date for a manually scheduled task, the date is simply entered as is, and Project does not assign a task constraint or make any other scheduling changes.

If you enter an actual finish date that is different from the scheduled finish date, Project changes the scheduled finish date to match the date in the Actual Finish field.

Best Uses    Add the Finish field to a task sheet when you want to review or filter for scheduled finish dates for tasks. The Finish field appears on the Gantt Chart view by default.

Example    You need to filter for all finish dates scheduled after March. You filter on the Finish field to see only those tasks scheduled with a finish date beyond March 31.

Remarks    In a manually scheduled task, you can enter a valid finish date, or you can enter text such as TBD or unknown. A manually scheduled task is considered a placeholder task until two of the three scheduling factors—start date, finish date, and duration—contain valid schedule information.

When you enter percent complete or actual work, Project might reschedule remaining work around the status date, and this can change the scheduled start date. If you prefer, you can leave these tracking fields in the project as originally scheduled, even if completed work is shown in the future or remaining work is shown in the past.

You can do this in the Project Options dialog box. Also, you can set the status date to a date other than today's date in the Project Information dialog box.

2 comments:

  1. I know of a group of private investigators who can help you with they are also hackers but prefer to be called private investigators They can help with your bitcoin issues and your clients will be happy doing business with you,they can also help yo with your bad credit score,hacking into phones,binary recovery,wiping criminal records,increase school score, stolen files in your office or school,blank atm etc. Just name it and you will live a better life
    whatsapp +1 (984) 733-3673
    telegram +1 (984) 733-3673
    Premiumhackservices@gmail.com

    ReplyDelete
  2. Are you looking for fast and effective credit hacks to boost your credit score and erase negative items from your record? Then I strongly recommend Metronet Credit Solution, they are fast, effective and legit. They came through for me when I thought all hope was lost. You can reach them on their mail: metronetcreditsolution@gmail.com

    ReplyDelete