Monday, May 3, 2021

Networkdays function

This article describes the formula syntax and usage of the NETWORKDAYS function in Microsoft Excel.

Description

Returns the number of whole working days between start_date and end_date. Working days exclude weekends and any dates identified in holidays. Use NETWORKDAYS to calculate employee benefits that accrue based on the number of days worked during a specific term.

Tip:  To calculate whole workdays between two dates by using parameters to indicate which and how many days are weekend days, use the NETWORKDAYS.INTL function.

Syntax

NETWORKDAYS(start_date, end_date, [holidays])

The NETWORKDAYS function syntax has the following arguments:

  • Start_date    Required. A date that represents the start date.

  • End_date    Required. A date that represents the end date.

  • Holidays    Optional. An optional range of one or more dates to exclude from the working calendar, such as state and federal holidays and floating holidays. The list can be either a range of cells that contains the dates or an array constant of the serial numbers that represent the dates.

Important:  Dates should be entered by using the DATE function, or as results of other formulas or functions. For example, use DATE(2012,5,23) for the 23rd day of May, 2012. Problems can occur if dates are entered as text.

Remarks

  • Microsoft Excel stores dates as sequential serial numbers so they can be used in calculations. By default, January 1, 1900 is serial number 1, and January 1, 2012 is serial number 40909 because it is 40,909 days after January 1, 1900.

  • If any argument is not a valid date, NETWORKDAYS returns the #VALUE! error value.

Example

Copy the example data in the following table, and paste it in cell A1 of a new Excel worksheet. For formulas to show results, select them, press F2, and then press Enter. If you need to, you can adjust the column widths to see all the data.

Date

Description

10/1/2012

Start date of project

3/1/2013

End date of project

11/22/2012

Holiday

12/4/2012

Holiday

1/21/2013

Holiday

Formula

Description

Result

=NETWORKDAYS(A2,A3)

Number of workdays between the start (10/1/2012) and end date (3/1/2013).

110

=NETWORKDAYS(A2,A3,A4)

Number of workdays between the start (10/1/2012) and end date (3/1/2013), with the 11/22/2012 holiday as a non-working day.

109

=NETWORKDAYS(A2,A3,A4:A6)

Number of workdays between the start (10/1/2012) and end date (3/1/2013), with the three holidays as non-working days.

107

Top of Page

No comments:

Post a Comment