Optimistic Finish (task field)
Data Type Date
Entry Type Calculated or entered
Description The Optimistic Finish field contains the date that represents the best-case possibility for when a task could finish. You can enter this date as part of a PERT analysis calculation, which takes a weighted average of expected, pessimistic, and optimistic dates and durations. This field is available only in the PA_Optimistic Case table or the PA_Optimistic Gantt view.
How Calculated When you first create a task, the Optimistic Finish date field contains "NA." When you enter an optimistic duration and optimistic start date, and then click Calculate PERT on the PERT Analysis toolbar, an optimistic finish date for the selected task is calculated and placed in the Optimistic Finish field.
Best Uses Use the Optimistic Finish field in the PA_Optimistic Case table or the PA_Optimistic Gantt view to estimate the probabilities of task dates. By default, the PERT analysis calculation gives heaviest weight (4) to the expected information, and the lightest weight (1 each) to the pessimistic and optimistic information.
Example You have several critical tasks for which you want to see the best-case, worst-case, and expected finish dates. You enter the expected start dates and durations for these tasks, as well as their optimistic and pessimistic start dates and durations, and then run the PERT analysis calculation.
Remarks By changing the weight that Microsoft Office Project attributes to each of the three estimated durations, you can tailor the probable estimate to be more accurate. To change the weight, click PERT Weights on the PERT Analysis toolbar, and then alter the default settings.
The Optimistic Finish field uses the Finish1 custom finish date field.
No comments:
Post a Comment