My resource assignment costs show a zero value
Symptoms
The resources that are assigned to your project task have associated costs, but the total costs for your resource assignments show a zero value.
Cause
The wrong cost rate table may be applied to your task.
Resolution
-
Check that all resources are assigned to tasks. Note that costs are calculated only after resources are assigned to tasks.
-
Check the cost rate table that you have applied to the task. A cost rate table that does not contain rates may have been applied. You can change the cost rate table for the resource assignment.
-
On the View menu, click Task Usage.
In the Task Usage view, resources are grouped by the tasks they are assigned to.
-
Select the resource who is assigned to the task for which you want to verify its associated cost rate table.
-
Click Assignment Information .
-
In the Cost rate table list, verify that the cost rate table is the correct one for the task.
-